Blog Layout

First Push at ACO

Otto Simon Ltd • September 5, 2016

Battery 3 of the Appleby Coke Ovens (ACO) at Scunthorpe, is back in business!

The first push of the newly restored battery was conducted in late July after an extensive recovery project which included the replacement of all 33 oven door frames, pulman valves and ascension pipe assemblies, and service pipework. In addition to this, several end flue repairs and extensive ceramic welding of the oven refractory was carried out.

The project took more than 250,000 man-hours to complete and was achieved whilst working between 2 live batteries with minimal disruption to normal operations; which enabled continued production of coke for British Steel’s blast furnaces.

The battery had been steadily declining in its ability to produce coke and gas, and was struggling to produce enough coke to sustain the blast furnaces. In December 2015 the decision was made to ‘Hot Idle’ the battery (hold the battery at a temperature of 950°C while the work was carried out) and repair works commenced in January 2016.

Otto Simon carried out the majority of the project, acting as Principal Contractor under CDM 2015. Nick Shaw, Otto Simons’ Head of Coke, Construction and Commissioning said: “It’s been a pleasure to work with British Steel on this project. We forged a strong and productive working relationship to make sure the project was delivered safely and on time. Despite challenges of working between operational batteries, a tremendous amount of effort and engineering has gone into bringing battery 3 back into production with a greatly improved environmental performance."

Otto Simon’s hard work and the coordination between project teams has been praised by British Steel’s Recovery Team Leaders, Chris Peill and Dale Cryer. Dale said "Every single person involved in the project should feel proud with what we've achieved”, with Chris commenting: “There was fantastic cooperation between production teams and the rebuild contractors to get the project finished on time.”

Thanks to the recovery project, the plant’s production volume of coke has almost doubled from 4.5kt to approximately 9kt. Jim Worsely, Plant Manager ACO said: “The combined benefit of coke and gas production from battery 3 will be approximately £12m year on year. ACO has had a very challenging but productive 12 months. Delivering a 50% improvement in our safety performance along with nearly doubling the plant output is an incredible achievement. The team at ACO has a lot to be proud of."

The project was not without its difficulties. Working between two live ovens provided numerous health and safety risks which were expertly managed during the project thanks to the additional control measures put in place. "During this phenomenal project, the only 'injury’ we had was a small blood blister, which is absolutely incredible and shows how dedicated the guys were," said Jim. The additional measures put in place for this project are now being rolled out across the rest of ACO’s operations.

Jon Campbell, ACO Recovery Manager told Steel Matters, British Steel’s in-house magazine: "It gives me great pleasure to see the end of the phase of battery 3. It's personally been one of the most difficult challenges - to make sure a project, a live recovery and the prime manufacturing process was planned in such a way that all parties achieved their goals."

The project was a huge success for all involved and shows a commitment to the future of the Scunthorpe site. British Steel will now start to look at repair works for Batteries 1,2 and 4. Otto Simon was delighted to work alongside British Steel on this project, and is looking forward to further collaborations on this site in the future.

 
Back to Blog

Recent Blog Posts

By Clees February 17, 2025
 Otto Simon has a unique selling point in comparison with the multitude of engineering contractors plying their trade to the chemical manufacturers in the North West of England. The North West chemical industry is of great importance to Otto Simon and we are dedicated in the provision of service and support to our chemical clients. Our USP? Otto Simon’s engineers have extensive experience of working on site and being in the ‘thick of it’. We know what the issues are, we understand the challenges, whether these arise from getting products to market on time, increasing manufacturing capacity or improving energy efficiency and being compliant with safety and emissions legislation. We can help. The North West is strong in chemical manufacture and accounts for 25.3% of the UK Chemical Sector GVA employing some 27,325 people, exports amount to £7.9bn and the data available from the CIA goes into greater depth to underline how our region is a significant strategic UK asset.
By Clees February 14, 2025
Otto Simon attended the two-day H2 Conference in Liverpool on the 5th and 6th of February at the Titanic Hotel.  There was cautious optimism on the part of the attendees in respect of the UK H2 developments as the economy currently has sluggish growth forecasts and the HAR 1 Contracts between the H2 producers and the Government are slowly reaching conclusion. HyNet is moving forward but at a pedestrian pace. Interest in hydrogen is high and there are more potential off-takers of H2 than there is projected supply over the next five years, but this imbalance is being addressed. Questions were raised about the current funding model, which if maintained, could add up to £200- £300 per year to the average domestic consumer’s household bill. It was suggested that just burning H2 as a natural gas replacement was a futile exercise, whereas using it to create energy from powering turbines and developing H2 storage would be a more economically effective use of H2. Apparently, Air Products is the world’s biggest global H2 producer with some 9,000 tonnes per day and they intend to grow this business. The EU has a plan to produce 1,000 tonnes per day and is on track to achieve this. The UK has some catching up to do. There were altruistic comments calling for greater collaboration in the sharing of innovative ideas and how to tackle emergent issues together which have arisen from the numerous H2 projects involving the H2 community. However, whilst this notion was tepidly received, the companies concerned, often in competition with each other to get awarded H2 projects, will remain naturally protective of their technologies, their IP and their commercial aspirations therefore co-operation will be somewhat limited and transactional. Cadent and others highlighted the planning issues associated with developing the intended H2 cross- county pipelines and urged the local authorities to work together. Modular Nuclear Generation was discussed. At the present there are only five sites in the UK where these can be legally located. The manufacturers stressed the safety case for considering locating reactors in areas where there are greater densities of population to supply energy closer to intended H2 facilities. A promising idea in principle?
By Clees February 12, 2025
We're thrilled to announce that Otto Simon has achieved Cyber Essentials certification! This significant milestone demonstrates our unwavering commitment to protecting all that we have been entrusted with in today's increasingly complex digital landscape. Cyber Essentials is a UK government-backed scheme designed to help organisations of all sizes protect themselves against common cyber threats. It provides a clear set of security controls that, when implemented correctly, significantly reduce the risk of cyber-attacks. Achieving this certification validates our dedication to maintaining the highest standards of cybersecurity and ensuring the confidentiality, integrity, and availability of information. What does this mean? In a world where cyber threats are constantly evolving, knowing that your partners prioritise security is paramount. Our Cyber Essentials certification provides the assurance that: We take data security seriously: We've implemented robust security measures to protect against common cyber threats, including malware, phishing, and hacking. Your data is in safe hands: We adhere to best practices for data handling and storage, minimizing the risk of data breaches. We're committed to continuous improvement: Achieving Cyber Essentials is not a one-time event. We will regularly review and update our security controls to stay ahead of emerging threats. We're a trusted partner: Our certification demonstrates our commitment to meeting industry-recognized security standards. What is Cyber Essentials? The Cyber Essentials scheme focuses on five key controls: Boundary Firewalls: Protecting our network from unauthorized access. Secure Configuration: Ensuring our systems are configured securely to minimize vulnerabilities. User Access Control: Restricting access to sensitive data based on roles and responsibilities. Malware Protection: Protecting our systems from malicious software. Patch Management: Keeping our software up to date to address known vulnerabilities. Our Ongoing Commitment Achieving Cyber Essentials certification is a significant step, but it's just one part of our ongoing commitment to cybersecurity. We will continue to invest in security measures, train our staff on best practices, and stay informed about the latest threats to ensure we maintain the highest level of protection. We believe that security is a shared responsibility, and we encourage everyone to be vigilant online. By working together, we can create a safer digital environment for everyone.
Show More
Share by: